Garney
Slide 1
Slide 2
Slide 3
Slide 4
Capitol Hill 04 Capitol Hill 03 Capitol Hill 02 Capitol Hill 01

Capitol Hill Recycled Water Tank (CM/GC)

The goal of this $11 million Construction Manager/General Contractor (CM/GC) project was to store and convey reuse water from Denver Metro’s large wastewater plant to irrigate parks and open space in the Denver metropolitan area. This was the latest project undertaken by the Denver Water Board as they moved forward with their commitment to reuse water. This project included three major portions of work. The first portion entailed the demolition of the 240,000 SF “Double T” roof, wall sections, and a portion of the base slab on an existing 29 MG tank, which totaled approximately 9,500 CY of concrete. The second portion of the project included the erection and backfill of a new 6 MG post-tensioned concrete tank at the demolished portions of the existing tank. And the third portion dealt with the placement of welded steel yard piping varying from 24″ to 60″ in diameter, one 120″ stand pipe, butterfly and cone valves, and manholes needed to put the new 6 MG tank into operation as a recycled water storage reservoir.

 

 

 

“Garney Construction’s expertise in tank construction and pipeline installation was a key factor in the success of the project. The strong working relationship Garney built with Denver Water ensured smooth communication and coordination with the project team, as well as subcontractors, external entities and the general public.”
 

Martin Garcia, Design Project Manager for Denver Water